Telephone
POTS lines for elevator and fire alarm systems have been installed and tested. Contractor provided emergency phones have been punched down into the college infrastructure and completion of the circuits and phones will be complete by Friday, Jan 15.
Network Engineering
The switch to support the building BAS, security and access control systems has been ordered. Deliver and install date will be finalized according to the construction schedule.
Cabling
College provided cabling has been completed and tested.